Singleton Gym + Swim upgrades

  • Project typeBuildings
  • Project value$2million
  • Completion Date31 December 2025
Gym and Swim

There’ll be plenty to splash about this summer with an all-new $1.5million water play attraction at Singleton Gym + Swim to be delivered just in time for the 2025 Christmas school holidays.

A splash pad will replace the existing outdoor toddler pool at the facility including spray jets, slides, fountains and interactive water play elements.

Construction will get underway on 31 July 2025, with completion slated in December 2025.

Upgrades to the changerooms, and car park (worth more than $400,000) are now completed, which included resurfacing, new line marking, signs and bollards to match the existing layout, and new solar-powered lighting installed.

Meanwhile the Gym + Swim Mechanical Upgrades Project is entering its final phase, with the wading pool soon to have its own dedicated filtration, chemical dosing, and heating system – separate from the 25m pool.

To make this happen, both the wading pool and 25m pool will be offline from 17 November 2025 and are expected to reopen on 31 March 2026, following the replacement of the dome structure.

We understand this is a long closure, particularly over the summer months, and thank our community for your patience while these essential upgrades are completed. The improvements will provide safer, more efficient, and higher-quality swimming experiences for everyone once the pools reopen.

 

 

 

Click here to download the Gym + Swim carpark works staging proposal

 

 

 

Location

14-16 Civic Ave, Singleton 2330  View Map