singleton town centre - Stage 2 upgrade

24 hour enquiry line 0401 096 484 or email singletontc@robsoncivil.com.au


ABOUT THE PROJECT

The modernisation of John Street is spreading, with the $7 million Town Centre - Stage 2 Upgrade  to continue Singleton’s transformation as a destination for retail, dining, recreation and leisure.

We are revitalising John Street from the Ryan Avenue intersection north to Campbell Street, and from Campbell Street to the New England Highway to enhance the gateways to the Town Centre from the highway as well as improve traffic flows and pedestrian connectivity.

Robson Civil has been appointed as the principal contractor, with construction work to begin on 27 July 2020 and continue for up to 12 months (weather permitting).

Click here to download the work notification - start of work letter that was circulated on 15 July 2020. 

WHAT'S HAPPENING NOW

  • Dilapidation Reports: On Wednesday 5 August 2020, a Robson Civil representative and a structural engineer will be doorknocking in the area to offer dilapidation reports to property owners.
  • Electrical investigation works: From Monday 3 August 2020 the following electrical investigation works will begin:
    • Inspection of the main switch board and electricity points of attachment. Workers from Robson Civil and subcontractor ARA will conduct inspections of the external mains switch board and Ausgrid network point of attachment to buildings in the area to allow for future connection planning. 
    •  Inspection of buildings for Ausgrid level 2 connections. For planning and procurement purposes, Robson Civil and subcontractor ARA will be accessing the Ausgrid network around the exterior of buildings to allow for future connection. 
  • Undergrounding of Electrical Services: From Monday 3 August 2020, excavation works will begin in order to relocate electrical services underground.
    • Electrical Undergrounding - Campbell Street: Workers from Robson Civil and subcontractor ARA will begin the electrical undergrounding works. The work zone will be in Baileys Union Park and the south side of Campbell Street between John and Bourke streets.
    • Electrical Undergrounding - John Street: Workers from Robson Civil and subcontractor ARA will begin electrical undergrounding works on the western footpath of John Street between Elizabeth and Macquarie streets. 

 This work will involve:

  • Removal of trees
  • Removal of pedestrian islands
  • Excavation of footpath, kerb and guttering
  • Saw cutting, jackhammering and the use of heavy machinery 
  • Temporary footpath barriers

 How will this work affect me?

Pedestrian and traffic access will be maintained. Traffic control will be in place as required and a temporary work zone speed limit of 40km/h will be in effect.

 When will work take place?

Most activity will be carried out from 7am until 6pm Monday to Friday.

 What equipment will be used?

Equipment will include, but is not limited to machinery haulage vehicles, trucks, excavators, light vehicles, power tools and hand tools.

 What to expect during construction

There may be some noise associated with this work. We apologise for the inconvenience and will aim to minimise the impact of our work by:

  • Turning off equipment when not in use, and
  • Positioning noisy equipment as far away as possible from residents and businesses.

DOWNLOAD MORE INFORMATION

MEET THE TEAM

Jason Brown

Jason Brown, site manager for Robson Civil, working on the Singleton Town Centre Upgrade

"I've only been in the area a short time, but I've found Singleton to be a friendly place, and a great place to raise a family. My partner has family in the Hunter, and we've both made a lot of good friends already. We love having friends and family over for a drink and a barbecue, or jumping on the Harley to explore, finding out what the region has to offer.

"After working as a quarry manager, I began working in the civil industry around 10 years ago. This project is an exciting one that will transform the town centre. I am focused on environmental management, as well the health and safety of my team and the general public. We are working hard to ensure that interruptions to the community will be kept to a minimum."

PROJECT FAQS

 What work will be done? 

Key construction activities involved in the project are:

  • Re-lining of existing storm water drains
  • Placing powerlines underground and connection of services to each building
  • Construction of new footpaths, kerbs and gutters
  • Landscaping and irrigation works
  • Installation of street lights, furniture, and signage

 When will the work be done ?

Most activity will be carried out from 6am until 6pm, Monday to Friday, and Saturday from 8am to 3pm, weather permitting. If we need to work outside these times, we will let you know.

Will traffic and parking be affected?

During construction there will be necessary changes to the traffic conditions and car parking in the precinct, however the project will be staged to ensure disruptions are kept to a minimum. We do this by ensuring construction is as efficient as possible so the project is completed in a timely fashion.

What about access to businesses?

Access to businesses will  be maintained with pedestrian diversions in place and changes to driveway access. Considered Traffic Management, Pedestrian Management and Construction Staging plans will be made public prior to the commencement of works to keep the public and stakeholders informed of upcoming activity. We acknowledge that, as with any major construction, there will be some short-term disruption. We will do our best to minimise these impacts and make sure that access is maintained throughout the project.

What next?

Buildings within the work precinct will be sent regular updates via mail to inform them of any upcoming work in their area or changes to scheduled work. These notifications will also be available on this page. Regular updates will also be posted on the Singleton Council Facebook page.

Contact

Thank you for your patience during these works. If you’d like to know more about the project, please contact our 24 hour enquiry line on  0401 096 484 or email singletontc@robsoncivil.com.au